Question
Find the average number of unsold cars on May and
July. Read the following information below and the answer the given questions: The table given below shows the total number of cars manufactured by company βXYZβ on five different months and the percentage of cars sold out of the total cars manufactured on that month. Note: (i) Total cars unsold in any given month are available for sell in next month. (ii) Total unsold cars on April is 20.Solution
Required average = (80 + 20)/2 = 50
A is four times as efficient as B and can finish a piece of work in 33 days less than B. B can finish this work in how many days?
Pawan completes 40% of a task in 6 days. His efficiency is 100% greater than Qureshi's. How many days will it take for both Pawan and Qureshi, working t...
The ratio of time taken by P, Q and R to complete work alone is 4:6:3 respectively. If all three together complete the work in 8 days, then find in how ...
Pooja can complete a task in 45 days and Kavita in 30 days. A third person, Mehul, is 20% more efficient than both of them combined. How many days will ...
x men can finish a work in y days. 0.9x women can finish 1/3rd of the same work in (y - 8) days. If 0.8x women can complete 1/3rd work in 36 days. Find ...
Anil and Ashish receive Rs.1500 for work of 5 days. If Anil is 4 times efficient than Ashish, then find the daily wage received by Ashish.
The ratio of time taken by P, Q and R to complete work alone is 6:8:3 respectively. If all three together complete the work in 5 days, then find in how ...
12 man can make a wall in 5 days. How many men required to complete the same work in 6 days ?
A can complete a work in 18 hours while B can complete it in 12 hours. If C is 80% more efficient than A and B together, then find the time taken by C a...
βAβ alone can complete a work in 40 hours. βAβ started the work alone and left after working on it for 20 hours. If βBβ completed the rest o...