Question
If Worker E works alone for 15 days, how many units of
the project will remain incomplete after this period? Direction: Five workers – A, B, C, D, and E – are working on a construction project to complete 500 units of work. Each worker works different numbers of hours per day and has varying work efficiencies, which are calculated as the number of units completed per hour. The following table shows the daily working hours and the efficiency (units per hour) for each worker:Solution
Total work done by E in 15 days = 15 × 9 × 1.8 = 243 units. Remaining work = 500 - 243 = 257 units.
Yellow colour in papaya is due to
The term for the reversible changes in morphology and physiology that plants employ to respond to changes in environmental conditions is?
Forking in carrot is observed, it occurs due to _____
A type of grafting in which shallow, downward and inward cut ensuring V-shape incision in lower portion of rootstock and matching cut on the scion is ma...
Mangla, Sumangla , Sreemangla are the popular varieties of which of the following crops?
Sinduri is variety of -
Maximum 'Kinnow' production in Rajasthan belongs to the districts.
Which of the following vegetable crop is rich in Vitamin C?
Lycopene development in tomato is adversely affected when temperature goes beyond ___
Aonla belongs to the family of……………………..