Question
If Worker E works alone for 15 days, how many units of
the project will remain incomplete after this period? Direction: Five workers – A, B, C, D, and E – are working on a construction project to complete 500 units of work. Each worker works different numbers of hours per day and has varying work efficiencies, which are calculated as the number of units completed per hour. The following table shows the daily working hours and the efficiency (units per hour) for each worker:Solution
Total work done by E in 15 days = 15 × 9 × 1.8 = 243 units. Remaining work = 500 - 243 = 257 units.
Under the simplified procedure for working capital finance to Micro and Small Enterprises (MSEs) with working capital limits of up to ₹5 crore, the wo...
Which one of the following is a correct equation?
Which among the following correctly describes Margin of Safety?
Customer acquisition costs (agent commissions) for one-year policies are paid upfront. Can they be capitalized as intangible assets?
A company purchased a machinery for Rs.4,50,000. The machine is expected to have a useful life is 7 years after which it can salvage a value of Rs.30,0...
According to section 10 of Indian Contract Act, 1872, which of the following is not regarded as the essential elements of a valid contract?
Which of the following is shown under investing activities in the cash flow statement ?
A company reports the following data for the year:
• Net Profit before tax and extraordinary items: ₹12,00,000
• Depreciation: ₹2,...
As per government procurement policy, Central Public Sector Enterprises (CPSEs) are required to procure what minimum percentage of their purchases from ...
Contribution is calculated as: