Let the length and breadth of the rectangular field be ‘p’ metres and ‘q’ metres respectively Then, according to the question, 2 × (p + q) = 34 Or, (p + q) = 34/2 = 17…… (1) Also p × q = 60 We know, (p + q)2 = p2 + q2 + 2pq Or, p2 + q2 = 172 – 2 × 60 Or, p2 + q2 = 169 So, length of the diagonal of the rectangular field = √(length2 + breadth2) = √(p2 + q2) = √169 = 13 metres
'P', 'Q', and 'R' can individually complete a task in 20, 24, and 30 days, respectively. They all started working together, but '...
A contractor hired 50 workers to complete a work in 80 days. After 50 days, it was found that only 1/4th of the work was completed. Find the number of e...
P and Q together can do a piece of work in 15 days, Q and R together can do it in 18 days. P starts the work and works on it for 5 days, then Q takes it...
A group of workers was put on a job. From the second day onwards, 1 worker left work everyday. If no worker was left when 52% of the work gets complete...
Tony has 3 sons – Harry, Peter and Murphy. Harry and Peter can complete the work in 24 days and 36 days respectively. In how many days Murphy will...
P can complete a piece of work in 15 days. Q in 20 days and R in 30 days. P and R worked together for three days and then P was replaced by Q. In how ma...
A and B together can complete a piece of work in 12 days, while B and C can complete it in 15 days. A, B, and C together can complete the same work in 8...
A and B can complete a work together in 30 days. If A alone can complete one-third of the work in ‘x’ days and remaining work is completed by B alon...
Working together, Amit and Pawan can finish a task in 22.5 days, and Pawan and Chirag can complete 60% of the same task in 14.4 days. Given that Amit is...