      Question

      β€˜P’, β€˜Q’ and β€˜R’ can complete a piece of

      work in 45 days, 60 days and 75 days respectively. β€˜P’ started the work and then β€˜Q’ joined him after 15 days. They together worked for 12 days and left the work. Find the time taken by β€˜R’ to complete the remaining work.
      A 12 days Correct Answer Incorrect Answer
      B 15 days Correct Answer Incorrect Answer
      C 18 days Correct Answer Incorrect Answer
      D 20 days Correct Answer Incorrect Answer

      Solution

      Let total amount of work = 900 units (LCM of 45, 60 and 75)

      Amount of work completed by β€˜P’ in one day = 900/45 = 20 units

      Amount of work completed by β€˜Q’ in one day = 900/60 = 15 units

      Amount of work completed by β€˜R’ in one day = 900/75 = 12 units

      Total amount of work completed by β€˜P’ in 15 days = 20 Γ— 15 = 300 units

      Amount of work done by β€˜P’ and β€˜Q’ together in 12 days = 35 Γ— 12 = 420 units

      Amount of work left = 900 – 300 – 420 = 180 units

      Time taken by β€˜R’ to complete 180 units of work = 180/12 = 15 days