Question

‘P’, ‘Q’ and ‘R’ can complete a piece of work in 45 days, 60 days and 75 days respectively. ‘P’ started the work and then ‘Q’ joined him after 15 days. They together worked for 12 days and left the work. Find the time taken by ‘R’ to complete the remaining work.

A 12 days
B 15 days
C 18 days
D 20 days