Question
‘P’, ‘Q’ and ‘R’ can complete a piece of work in 45 days, 60 days and 75 days respectively. ‘P’ started the work and then ‘Q’ joined him after 15 days. They together worked for 12 days and left the work. Find the time taken by ‘R’ to complete the remaining work.
More Addition & subtraction Questions
- There are total 200 students in a school, of which 1/5 are boys. Find the number of girls in the school.
- The efficiency of a woman is 33.33% less than that of a man, whose efficiency is three times that of a child. If 2 children, 3 women, and 4 men together ca...
- A sum of Rs.8200 is to be divided among 6 brothers, 5 sisters and 2 aunts. If each sister receives thrice as much as each aunt and each brother receives fo...
- Question 4
- If × stands for addition, ÷ stands for subtraction. + stands for multiplication and ̶ stands for division, then what is the valu...
- Select the correct set of symbols which will fit in the given equation. 5 0 3 5 = 20
- Which of the following shortcut key use to check Spellings in MS Office?
- Simplify: (2x)²-(2y)²-(4x)²
- Evaluate
- How much money did Miss Mishra receive as retirement fund? I. Out of the total money received, Miss Mishra gave 20% to her husband and 15% to her daughter...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt