Question
‘P’, ‘Q’ and ‘R’ can complete a piece of work in 45 days, 60 days and 75 days respectively. ‘P’ started the work and then ‘Q’ joined him after 15 days. They together worked for 12 days and left the work. Find the time taken by ‘R’ to complete the remaining work.
More Addition & subtraction Questions
- Two numbers P and Q are in the ratio 5:8. If X is added to the smaller number and 12 is subtracted from the larger number, the new ratio of P and Q becomes...
- The following chart gives the expenditure incurred by a publisher to bring out a book Find the percentage of the total expenditure incurred for printing.
- 24.89² ÷ (34.33 ÷ 20.02) + 67.85 – 89.01 = ?
- __________is the process that connects to a network without the use of cables.
- If sin x = 4/5, then Cosecx + Cot X =
- To justify the selected text, the shortcut key is __________.
- ‘P’, ‘Q’ and ‘R’ can complete a piece of work in 45 days, 60 days and 75 days respectively. ‘P’ started the work and then ‘Q’ joined him after 15 days. The...
- The mean deviation of the data 3, 10, 10, 4, 7, 10, 5 is:
- Consider a two-digit number where the ratio of the unit digit to the tens digit is 2:3. If the total of these digits equals 15, what is the product of the ...
- If × stands for addition, ÷ stands for subtraction. + stands for multiplication and ̶ stands for division, then what is the value of 20 × 8÷ 8 - 4 + 2 ...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)