X men can complete the piece of work in 32 days and (X + 30) men can complete the same work in 15 days less than that of days taken by X men. Find the v...
A and B can complete a piece of work in 12 days and 15 days respectively. They start working together, but after 4 days, A leaves. In how many more days...
‘A’ and ‘B’ can do a piece of work in 20 days and 32 days, respectively. If they started the work together and worked on it for 9 days, then fin...
‘A’ alone can complete a work in 40 hours. ‘A’ started the work alone and left after working on it for 20 hours. If ‘B’ completed the rest o...
- A group of 36 boys works 13 hours per day and completes 37.5% of a task in 20 days. After these 20 days, 'X' boys leave the job. The remaining boys continu...
‘A’ and ‘B’ can complete a certain work in 18 days and 20 days, respectively. They started working together and worked till completion of the wo...
30 men can complete a piece of work in 11 days. 15 men started the same work and worked for 8 days, and then joined by ‘x’ more men such that the re...
35 typists working 9 hours per day can complete a typing job in 14 days. ____ typists working _____ hours per day can complete (3/4)th part of the work ...
Armaan and Bhanu jointly received Rs. 9,000 for completing a task, with Bhanu's share being Rs. 3,000. If Bhanu can complete the work on his own in 48 d...
A can complete a task 40% more efficiently in 25 days, whereas B, with a 25% efficiency boost, can finish the same task in 21 days. They collaborated at...