Question
A man is 60% more efficient than a boy. Together, two
boys and one man can finish a task in 15 days. How many boys would be needed to complete the same task in 13.5 days?Solution
Let the efficiency of a boy = '5x' units/dayThen, efficiency of a man = 5x X 1.6 = '8x' units/daySo, combined efficiency of 2 boys and 1 man = 5x X 2 + 8x = '18x' units/daySo, total work = 18x X 15 = 270x unitsSo, number of boys required to complete the work in 13.5 days = (270x ÷ 13.5) ÷ 5x = 4
- Find the wrong number in the given number series.
3, 28, 253, 858, 2103, 4128 - Find the wrong number in the given number series.
9, 8, 18, 51, 208, 1045 Find the wrong number in the given number series.
20, 33, 50, 69, 93, 121
124, 132, 118, 140, 108, 148
12, 23, 35, 47, 59, 73
Find the wrong number in the given number series.
10, 17, 26, 39, 59, 85
- Find the wrong number in the given number series.
10, 19, 3, 28, 5, 54 1001, 934, 863, 790, 711, 630, 539
2400,3600,5400,7200,12150
P, Q and R invested their capitals in a business in the ratio 5:6:4 respectively. At the end of the year, they received profits in the ratio 10:18:8 res...