A alone can complete a piece of work in 15 days, while B alone can complete it in 20 days. They start the work together, and after some days A leaves. B completes the remaining work in 6 more days. For how many days did A and B work together?

A 2 days
B 6 days
C 10 days
D 19 days
E None of these