A and B can complete a task together in 8 days, while B
alone takes 16 days to finish it. A began working alone and left after ‘x’ days, after which B completed the remaining work in 12 days. Determine the percentage of the total work completed by A.Solution
Let total amount of work be 16 units
Efficiency of (A + B) = 16/8 = 2 units/day
Efficiency of ‘B’ = 16/16 = 1 unit/day
Amount of work done by ‘B’ = 12 × 1 = 12 units
Percentage of work done by ‘A’ = {(16 – 12)/16} × 100 = 25%
Who has been appointed as the brand ambassador of Fit India Movement in February 2024?
Consider the following statements in relation to GI tags:
1. Lanjia Saura paintings, Dongaria Kondh shawl, Khajuri Guda received GI tags in Jan 2...
Which organization implemented the floating solar power plant in Ramagundam, Telangana?
Which city was recently renamed as “Shri Vijayapuram”?
- What is the name of the simplest hydroxy derivative of benzene?
- Popir is a traditional dance form of which tribal community of Arunachal Pradesh?
Which airport was ranked as the busiest airport overall in 2022, according to the rankings released by Airports Council International?
- Who did the Ministry of Law and Justice appoint as the Chief Justice of the Orissa High Court in March 2025?
Kasturba Gandhi Balika Vidyalaya provides:
- A natural geo-hydrological unit of land that collects water and drains it through a common point by a system of streams is called a: