Question
A and B can complete a task together in 8 days, while B
alone takes 16 days to finish it. A began working alone and left after ‘x’ days, after which B completed the remaining work in 12 days. Determine the percentage of the total work completed by A.Solution
Let total amount of work be 16 units
Efficiency of (A + B) = 16/8 = 2 units/day
Efficiency of ‘B’ = 16/16 = 1 unit/day
Amount of work done by ‘B’ = 12 × 1 = 12 units
Percentage of work done by ‘A’ = {(16 – 12)/16} × 100 = 25%
If A = (7)1/3 + (7) -1/3, then the value of {3A3 – 9A} will be:
If 1/(x+ 1/(y+ 1/z)) = 13/30, then find x+y+z= ?
If (5x - 2y) = 170 and 4x:3y = 32:9, then find the value of (3x² + y²).
If 2x + (1/9x) = 5, then find the value of 81x2Â + (1/4x2) - (1785/4)
If ( p = 60 - q - r ) and ( pq + r(q + p) = 1080), then find the value of ( p2 + q2 + r2).
If a = 7.250, b = 3.258 and c = 3.992 then value of a3-b3-c3-3abc is.
If (x – 3) is a factor of (x2 + 4qx – 2q), then the value of q is:
- Find the value of (21)³ + (- 12) ³ + ( - 9)³.
A solid metallic sphere of radius 15 cm is melted and recast into spherical balls of radius 3 cm each. What is the ratio of the surface area of the orig...