Question
A team of 16 men works 9 hours a day and completes a
task in 40 days. If the goal is to finish the same task in 30 days, with each man working 8 hours a day, how many additional workers need to be hired to meet the new deadline?Solution
Let the total work be 'w' units/day Let number of men required to finish the new work be 'm' and efficiency of each man be 'e' units/hour ATQ; w/(16 x 9 x 40 x e) = w/(m x e x 8 x 30) m =Â 24 So, 24 - 16 = 8 additional men should be hired.
What does HTML stand for in web technology?
Which layer of the OSI model provides flow control, error checking, and reliability in data transmission?
In C programming, which header file is commonly used to work with DMA?
What is the data transmission direction in a Token Ring network?
Store data in single table
State true/false
Once the email is compromised, all other sites and services online associated with this email can be compromised.
Which of the following backup types provides the fastest backup and recovery performance but requires the most storage space?
What is the purpose of a semaphore in synchronization?
In which programming language is dynamic memory allocation commonly used?
What does the term "phishing" refer to in the context of cybersecurity?