Question
60 boys can complete a piece of work in 60 days. They
started the work together. But at the end of every 10th day five more boys have joined. Exactly on which day will the whole work be completed?Solution
ATQ, Required boys -hrs = 60 × 60 = 3600 boys-hrs. Boys-hrs completed in fifty(50) days = 10(60 + 65 + 70 + 75 + 80) = 3,500. Hence Balance left = 3600-3500 = 100 Let X days be required to complete the remaining 100 boys- hrs. Now, (x)(85) = 100 x = 1(3/17) days i.e., work is completed in 51(3/17) days i.e., on 52 nd day work is completed.
What is the square root of 5476?
Find the Square root of √14641
What is the smallest natural number that should be added to 1030 so that the square root of the sum is a natural number?
If the average of two numbers is 13 and the square root of their product is 12, then the difference between the numbers is:
Solve the following :-
Two times a number, added to the square of that number, gives 3. What could be the possible answer for this number?
Find the Square root of √1681
Find the square of 572
Find the square root of 0.0324.
A horse is tethered to a peg fixed at one corner of a rectangular grass field measuring 45 metres in length and 25 metre...