Question
150 unit of work can be completed by P alone in 25 days.
P started working alone and joined by Q after 15 days such that they completed the remaining work in 6 days. Find the number of days taken by Q to complete the whole work alone.Solution
Let the efficiency of Q = x units/day Efficiency of P = (150/25) = 6 units/day According to question: 6 × 15 + (6 + x) × 6 = 150 Or, 90 + 36 + 6x = 150 Or, 6x = 150 – 126 Or, 6x = 24 Or, x = 4 Number of days taken by Q to complete the work alone = (150/4) = 37.5 days
Which of the following potential is always negative?
In CRD design the degree of freedom for error is calculated by which formula?
Marconi wheat is known as:
Which crop is called 'camel crop"?
The synthesis of ATP via electron flow through the ETS, with oxygen as the terminal electron  acceptor,   is  known...
According to latest Final estimates of Foodgrain production 2023-24, Which state is the largest producer of sugarcane in India?
Tikka disease of groundnut spreads fast under the conditions of:
Pradhan Mantri Krishi Sinchai Yojana (PMKSY) was launched in the year___
What is the meaning of the word "Chrysanthemum," as derived from its etymology?
Of which South-East-Asian country did Joko Widodo become the President in 2019 for the second time?