📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!

  • google app store apple app store

    • Question

      A and B together can complete a piece of

      work in 40 days while B and C together can complete the same work in 55 days. All of three together can complete 80% of the whole work in 26.4 days then find the time taken by A and C together to complete the whole work. Note: You have to find approx. value
      A 52 days Correct Answer Incorrect Answer
      B 57 days Correct Answer Incorrect Answer
      C 50 days Correct Answer Incorrect Answer
      D 55 days Correct Answer Incorrect Answer
      E 60 days Correct Answer Incorrect Answer

      Solution

      Time taken by A, B and C together to complete the whole work = 26.4/0.80 = 33 days
      Let total amount of work = 1320 (LCM of 40, 55 and 33)
      Efficiency of (A + B) = 1320/40 = 33 units per day
      Efficiency of (B + C) = 1320/55 = 24 units per day
      Efficiency of (A + B + C) = 1320/33 = 40 units per day
      Efficiency of A = 40 – 24 = 16 units per day
      Efficiency of C = 40 – 33 = 7 units per day
      Desired time = 1320/23 = 57.4 days = 57 days