Question
A train travels a certain route in 250 minutes at a
speed of 48 km/h. If the same journey is done by bus in 5 hours, what should be the speed of the bus?Solution
ATQ,
When distance is constant,
Time ∝ 1/Speed
5 hours = 5 × 60 = 300 minutes
(Speed of train) ÷ (Speed of bus) = 300 ÷ 250 = 6:5
Speed of bus = (5/6) × 48 = 40 km/h
18 skilled workers can complete a task in 12 days while 24 semi-skilled workers need 15 days to complete the same task. 12 skilled workers started the t...
Pawan and Qureshi can complete a task in 12 days, while Pawan and Rishi can finish the same task in 40/3 days. Initially, Pawan a...
When 24 men work for only 3 days, 5/6th of work remains unfinished. How much work will remain unfinished if 27 men work for only 2 days?
'X' and 'Y' can complete a certain job together in 36 days. They worked together for 20 days, after which 'X' left, and 'Y' completed the remaining work...
4 girls can do work in 8 days, 3 boys can do the same work in 9 days, 7 men in 2 days, and 5 women in 4 days. Who is the least efficient?
Veer can complete a work in X days and Ayush is 40% more efficient than Veer. If both complete 4/7th of work together and get Rs. 1200 for it...
The time taken by ‘A’ to complete a task is 6 days more than the time taken by A and B together. If A is twice as efficient as B, find the time requ...
A and B can complete a task in 6 days working together. A alone works twice as fast as B. If A works alone for 2 days and B finishes the rest, how many ...
‘A’ and ‘B’ together can complete a work in 10 days, while ‘B’ and ‘C’ together can complete the work in...
Billy, Tony and Mike were three workers, employed by a Contractor. They completed the whole work in 20 days. Initially all of them worked together, but ...