Question
A and B can complete a task in 12 days and 16 days
respectively. They start working together but B leaves after 4 days. In how many more days will A complete the remaining work?Solution
Work done by A and B in 1 day = (1/12) + (1/16) = 7/48 Work done in 4 days = 4 × (7/48) = 28/48 = 7/12 Remaining work = 1 - 7/12 = 5/12 Work done by A in 1 day = 1/12 Time taken by A to complete the remaining work = (5/12) ÷ (1/12) = 5 days Correct Option: a
Which of the following Statements about IREDA is/are True?
I- It is registered as Non-Banking Financial Company (NFBC) with Reserve Bank of India...
Which of the following Statements about Multiplier Effect is/are True?
I- When the government spends a rupee, overall income rises by a multiple ...
What is the basic difference between Gross NPA and Net NPA?
I- Gross NPA is the total of Bank loans and Net NPA is the total of all kinds of loan...
Consider the following statements regarding Phase II of the Swachh Bharat Mission (Grameen) [SBM (G)]
1) The program will be implemented...
Which of the following statements about Prompt Corrective Action is/are True?
I-Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Prompt Corrective Action F...
Who among the following is not one of the eligible beneficiaries of PMUY?
When Government expenditure is more than income, through which of the following ways, it does the deficit financing?
(1) From Banks
(2) Fr...