Question
A can complete a work in 15 days, and B can complete the
same work in 20 days. If they work together for 6 days, what fraction of the work is left?Solution
Work done by A in 1 day = 1/15 Work done by B in 1 day = 1/20 Work done by A and B together in 1 day = (1/15 + 1/20) = 7/60 Work done in 6 days = 6 × 7/60 = 7/10 Fraction of work left = 1 - 7/10 = 3/10 Correct answer: d
The characteristic garlicky odour of garlic is due to _________.
Identify the ore from which Aluminum is extracted
Jaundice is caused due to malfunctioning of:
Which of the following statements about the MSME Minister Narayan Rane's initiatives at the 9th SHAKTI International Women Entrepreneurs Summit is/are c...
Where in India the Asia's largest Sports Institute ‘National Sports Institute’ is situated?Â
Who among the following was the first elected King of the Pala Dynasty in Kamarupa?
 What is India’s position in the world on the basis of per capita water availability per year ?
What is the tenure of the Sustainability-linked bonds issued by Mindspace Business Parks REIT?
What is the primary objective of the Assam Tourism Development and Registration Bill 2024, recently approved by the Assam cabinet?
What exactly is UHT processing used for processing?