Question
A can complete a work in 15 days, and B can complete the
same work in 20 days. If they work together for 6 days, what fraction of the work is left?Solution
Work done by A in 1 day = 1/15 Work done by B in 1 day = 1/20 Work done by A and B together in 1 day = (1/15 + 1/20) = 7/60 Work done in 6 days = 6 × 7/60 = 7/10 Fraction of work left = 1 - 7/10 = 3/10 Correct answer: d
What is the value of acceleration due to gravity at the center of the earth?
If an agent does a work 'W' in time 't', then the power is given by:__________.
A string of length L is fixed at both ends. It supports a standing wave with 3 antinodes. If the speed of the wave on the string is v, what is the freq...
Which physical quantity has unit “Joule/second”?
Which Bohr postulate explains the stability of the hydrogen atom?
A particle is moving in a uniform circular motion with constant speed v along a circle of radius r. The acceleration-of the particle is –
A ray of light travels from glass (n=1.5) to air (n=1). For which angle of incidence will the ray just graze the surface (total internal reflection limit)?
A body is projected upwards with an initial velocity u . At the highest point, what is its acceleration?
In a spring-block system executing SHM, at displacement x= A/2, the ratio of kinetic to potential energy is:
A particle of mass m is placed in a potential V(x) = ax² + bx⁴. For small oscillations around equilibrium, its time period is: