Question
A can do a certain work in 15 days and B can do
one-third of the same work in 10 days. A and B work together for 6 days and then A leaves. B completes the remaining work with C in 8 days. A and C together can complete the original work inSolution
B can do the work in = 30 days Let us suppose C can do the same work in x days. Now, A and B can do the part of work in 1 day is. Therefore, A and B can do the work together in 10 days, but they only did for 6 days. and the part of work done in 6 days is =6/10 th part of work. Now, The Remaining work = 1-10/ 6 =2/5 th part of work. Â Now, according to question B and C did the remaining work in 8 days Hence, in 1 day work done by B and C together is = 1/20th part of work Therefore, one day work of B and C together is =1/ 30 +1/x But it is given =1/ 20 as B and C does 2/5th part of work in 8 days
P can do a piece of work in 15 days, Q can complete double the work in 40 days and R can do the work in 20 days. If all of them together earn Rs. 3000, ...
- Alex and Ben can complete a job individually in 14 days and 21 days, respectively. If they take turns to work one day each, beginning with Alex, how long w...
‘X’ and ‘Y’ can do a task together in 15 days. If ‘X’ alone takes 25 days to complete it, then how much time will ‘Y’ take to finish the...
‘P’ and ‘Q’ can complete a task together in 24 days. If ‘P’ alone can do it in 40 days, find the number of days ‘Q’ alone will take to f...
A can complete a work in 40 days. B takes 20 days less than A to complete the same work. In how many days can both of them together complete 90% of the ...
P can do a piece of work in 30 days. Q do the same work in 40 days. R can do it in 35 days. P and R worked for 4 days and handed it to Q. Q worked for s...
X can do a piece of work in 15 days. He worked at it for 3 days and then Y finished it in 16 days. In how many days can X and Y together finish the work?
A job is done by 15 men in 30 days and 30 women in 20 days. How many days will it take for 8 men and 12 women to finish the work?
P can do a piece of work in 20 days, Q can do the same piece of work in 24 days while R can do it in 30 days. They started working together but after 4 ...
12 engineers complete designing 180 blueprints in 15 days. If the goal is to complete 270 blueprints in 18 days, how many engineers are required?