Question
The angle of elevation of the top of a tower from the
top of a building whose height is 680 m is 45° and the angle of elevation of the top of same tower from the foot of the same building is 60°. What is the height (in m) of the tower?Solution
ATQ, Let AB be the tower and CD Be the building (680m) and E Be the point Then, BE = 680m AE = h and CE = BD = 6 Then, (h/6) = tan 45° = 1 h=6 then, (h + 680m)/6 = tan 60° = √3 (h + 680m) = √3 b (h + 680m) = √3 h (√3 - 1) h = 2 (340) (√3 - 1)h/340 = (√3 - 1) (√3 + 1) (√3 - 1) is common and cancelled out from both sides h = (√3 + 1) 340Â
- ‘P’ and ‘Q’ together can finish a task in 15 days while ‘Q’ alone can do it in 25 days. If the ratio of efficiencies of ‘P’ and ‘R’ is ...
If 12 men can build a wall in 15 days, how many men are required to build the same wall in 10 days?
16 men can complete a work in 10 days. 10 men started the same work and left after working for ‘y’ days. The remaining work is completed by 6 men in...
"Akash and Bittu can individually complete a task in 40 days and 50 days, respectively. They start working together, and after 10...
Manoj can complete a job in 10 days which Rakesh can do in 15 days. Rakesh can finish a task in 20 days which Suresh can complete in 25 days. In how man...
- If Rina can complete a project in 36 days by working 9 hours a day, how many hours per day should she work to complete the project in 18 days?
‘A’ and ‘B’ can complete a certain work in 16 days and 32 days, respectively. They started working together and worked till completion of the wo...
- Pipe ‘X’ can fill a tank 15 minutes faster than Pipe ‘Y’. If both are opened together, they can fill the tank in 18 minutes. If 180 litres of water...
3 workers paint 5 rooms in 8 days. How many workers are needed to paint 10 rooms in 6 days?
28 men can complete a work in 20 days. 40 women can complete the same work in 28 days. 20 men and 12 women started working and after 16 days, 20 more wo...