      Question

      P, Q, R can do a piece of work in 40 days, 90 days, and

      36 days, respectively. P started the work. Q joined him after 7 days. If R joined them after 8 days from the beginning, then for how many days did R work?
      A 11(8/23) Correct Answer Incorrect Answer
      B 12(8/23) Correct Answer Incorrect Answer
      C 15(8/23) Correct Answer Incorrect Answer
      D 13(8/23) Correct Answer Incorrect Answer

      Solution

      LCM (40, 90, 36) = 360 Let the total work be the LCM of the time taken individually by the workers. Efficiencies, P does each day = 360 40 = 9 units Q does each day = 360 90 = 4 units R does each day = 360 36 = 10 units Let the total work be completed in K days. According to the question, 9 x K + 4 x (K-7) + 10 x (K - 8) = 360 23K= 468 K = 468/23 (K-8) =284/23 Β  (K - 8) = 12(8/23)