Question
P, Q, R can do a piece of work in 40 days, 90 days, and
36 days, respectively. P started the work. Q joined him after 7 days. If R joined them after 8 days from the beginning, then for how many days did R work?Solution
LCM (40, 90, 36) = 360 Let the total work be the LCM of the time taken individually by the workers. Efficiencies, P does each day = 360 40 = 9 units Q does each day = 360 90 = 4 units R does each day = 360 36 = 10 units Let the total work be completed in K days. According to the question, 9 x K + 4 x (K-7) + 10 x (K - 8) = 360 23K= 468 K = 468/23 (K-8) =284/23 (K - 8) = 12(8/23)
Simplify:
6x + 8y - [(12x + 6y) - (4x + 3y) + 2y] - 4xIf 9x2 + 16y2 = 24xy, then find the ratio of ‘x’ and ‘y’, respectively.
- Suppose [a + (1/16a)] = 3, then the value of [16a³ + (1/256a³)] is:
If, 6x + y = 20, and 2xy = 32, and 6x > y, then find the value of 216x³ – y³.
If x + 1/x = 2, find x⁷ + 1/x⁷.
(x – 6) 2 + (y + 2) 2 + (z – 4) 2 = 0, then find the value of 4x - 3y + z.
Three cubes of metal whose edges are 3cm, 4cm and 5cm. respectively are melted and a single cube is formed. What is the length of the edge of the newly ...
A number is increased by 20%, and the resulting number is decreased by 20%. If the initial number is ₹x, the final number is ₹2880. What is the valu...