Question
In a test, P got 30% of total marks and failed by 30
marks while Q got 40% of total marks which is 22 more than passing marks. Find the total marks of the test.Solution
Let the total marks of the test be βxβ Therefore, marks scored by P = 0.3x Therefore, passing marks of the test = 0.3x + 30 Marks scored by Q = 0.40x Also, passing marks of the test = 0.40x β 22 Therefore, 0.3x + 30 = 0.4x β 22 Or, 0.1x = 52 Or, x = 52/0.1 = 520 Therefore, total marks of the test = 520
- A builder employed 12 workers to complete a job in 18 days. But after 8 days, 4 workers quit. How many more days will be required to complete the remaining...
Sachin can complete a job in 15 days. Ankit alone can complete the same job in 10 days. Sachin works for 9 days and then the remaining job is completed ...
Akhil and Nikhil together can complete a work in 12 days while Nikhil alone takes 18 days to complete 25% of the work. If the efficiency of Sachin is 20...
- If a group of 8 boys and 12 girls can complete a task in 40 days, and a team of 4 girls alone can finish the same task in 80 days, how long will it take fo...
P and Q individually can complete the work in 36 days and 54 days respectively. If the time taken by R alone to complete the work is 1.25 times the time...
15 men can do a work in 30 days. After 18 days of work, 5 more men were engaged to finish the work. The number of days required to complete the remainin...
A, B and C alone can complete a work in 30, 60 and 45 days respectively. All of them started working together but after 3 days from start A left the job...
Rahul is 50% more efficient than that of Ramu. If Ramu can complete the work in 20 days, then find the time taken by both of them to complete 50% of the...
βDβ and βEβ together can finish a task in 40 days, while βEβ and βFβ together can finish the same task in 30 days. βDβ and βEβ t...
5 men and 10 women can do some work in 3 days. If each man is 150% more efficient than a woman, then find the time taken by 9 men to finish the same wo...