Question
Two contractors, X and Y, are assigned to finish a
construction project that consists of three phases. Each contractor works at a constant rate for each phase. What is the total number of hours taken by Contractor X to complete all three phases? Statements: 1. The total hours worked by Contractor Y on all three phases is 80% of the total hours worked by Contractor X. Contractor Y worked for 200 hours in the first phase, 300 hours in the second phase, and 250 hours in the third phase. 2. Contractor X spent twice as much time on the first phase as Contractor Y. Contractor X's time spent on the second phase is 150% of the time spent on the first phase.Solution
From Statement 1: Contractor Y’s total time is 200 + 300 + 250 = 750 hours. This is 80% of the time taken by Contractor X, so Contractor X’s total time is 750 / 0.8 = 937.5 hours. this alone is sufficient. From Statement 2: Contractor X’s time in the first phase is twice Contractor Y’s, So without help of statement 1 answer can’t be calculated. Statement 2 alone is not sufficient. Correct Answer: (a) Statement 1 alone is sufficient, but statement 2 alone is not sufficient.
Find the wrong number in the series given below.
7, 22, 68, 217, 625, 1880
Select the number from among the given options that is wrong in the following series.
22, 30, 46, 78, 146, 270
Find the wrong number in the given series.
60, 65, 75, 95, 125, 195, 355Â Â
Arrange the following words in a logical and meaningful order.
1. Monkey
2. Elephant
3. Rat
4. Fly
5. Lion
Find the wrong number in the given series.
17, 17, 51, 255, 1789, 16065
A series is given with two wrong terms. Select the wrong term in the given series.
32, 43, 58, 73, 92, 117, 144
A series is given with one wrong term. Select the correct alternative from the given ones that will complete the series.
33, 44, 66, 110, 199, 374
Select the wrong term in the series.
44, 47, 41, 50, 38, 53, 40
5, 15, 30, 135, 405, 1215, 3645
Find the wrong number in the series given below.
5, 16, 50, 157, 463, 1394