Question
Two contractors, X and Y, are assigned to finish a
construction project that consists of three phases. Each contractor works at a constant rate for each phase. What is the total number of hours taken by Contractor X to complete all three phases? Statements: 1. The total hours worked by Contractor Y on all three phases is 80% of the total hours worked by Contractor X. Contractor Y worked for 200 hours in the first phase, 300 hours in the second phase, and 250 hours in the third phase. 2. Contractor X spent twice as much time on the first phase as Contractor Y. Contractor X's time spent on the second phase is 150% of the time spent on the first phase.Solution
From Statement 1: Contractor Y’s total time is 200 + 300 + 250 = 750 hours. This is 80% of the time taken by Contractor X, so Contractor X’s total time is 750 / 0.8 = 937.5 hours. this alone is sufficient. From Statement 2: Contractor X’s time in the first phase is twice Contractor Y’s, So without help of statement 1 answer can’t be calculated. Statement 2 alone is not sufficient. Correct Answer: (a) Statement 1 alone is sufficient, but statement 2 alone is not sufficient.
Development of a diploid (2N) embryo from nuclear of integumentary tissue isÂ
Nucleic acids are:Â
…………………silkworm spp. Is commonly reared in Ricinus communis
What is the critical growth stage in wheat when moisture stress can cause maximum yield reduction due to impaired pollination and grain setting?
Transfer of Ownership is an example of which utility
The carbon dioxide concentration in the atmosphere is:
The most commonly used hybridization method in crop improvement is:
What is the objective of Krishi 24/7, the AI-powered solution developed by DA&FW, Wadhwani AI, and Google.org?
Where do grasshoppers lay eggs?
In onion, smell occurs due to the presence of?