Question
A and B together can complete a work in 12 days. B and C
together can complete the same work in 15 days, and A and C together can complete it in 20 days. How long will it take for A, B, and C to complete the work if all three work together?Solution
A+B = 12 days B+C = 15 days C+A = 20 days Let the total work has to be done by them = LCM of 12, 15, 20 = 300 A+B works in one day = 300/12 = 25 unit B+C works in one day = 300/15 = 20 unit C+A works in one day = 300/20 = 15 unit A+B+B+C+C+A = 25+20+15 = 60 unit A+B+C = 60/2 = 30 units Time taken to finish the work by A+B+C = 300/30 = 10 days
Fresh water fishery accounts for……………….% of total production in India
Among the following, which has recently organized a national conclave on soil health management for sustainable farming on the occasion of the World Soi...
The Mobile app which was developed by the Ministry of Rural Development to capture the ground water level in a better way.
Which of the following soil is suitable for growing cereals, oilseeds and citrus fruits and also for cotton cultivation?
The National centre for agriculture economics and policy research is located at?
On 24 April_____, the Constitutional (73rd Amendment) Act 1992 came into force to provide constitutional status to the Panchayati Raj institutions.
With reference to direct seeding of rice (DSR), consider the following statements:
1. Direct-seeded rice matures 7 to 10 days earlier than tra...
Rural Infrastructure Development Fund (RIDF) is under
The world’s largest coral reef isÂ
India’s first greenfield grain based ethanol production plant inaugurated in ………………….