Question
A and B together can complete a work in 12 days. B and C
together can complete the same work in 15 days, and A and C together can complete it in 20 days. How long will it take for A, B, and C to complete the work if all three work together?Solution
A+B = 12 days B+C = 15 days C+A = 20 days Let the total work has to be done by them = LCM of 12, 15, 20 = 300 A+B works in one day = 300/12 = 25 unit B+C works in one day = 300/15 = 20 unit C+A works in one day = 300/20 = 15 unit A+B+B+C+C+A = 25+20+15 = 60 unit A+B+C = 60/2 = 30 units Time taken to finish the work by A+B+C = 300/30 = 10 days
Below are given some parts of a sentence in jumbled order. Arrange the parts in the correct order to make a meaningful sentence.Â
1) land area i...
In which schedule of constitution lists are described?
Central Arid Zone Research Institute is situated in -
What is the nitrogenous waste excreted by shark?
- Which Indian state has the largest forest cover by area?
The Constitution (Scheduled Tribes) Order (Amendment) Bill, 2021, was introduced in Rajya Sabha by whom among the following Ministers for Tribal Affairs?
Where is Bilaspur located in India?
The first state in India to introduce a pension scheme for third genders is
The functions of NITI are
(1) Decentralized Planning
(2) Harmonization
(3) Capacity Building
(4) External Consultan...
Rajasthan's first 'solar lift plant' will be built on which river?