1) Negative Demand Negative demand occurs when a product is disliked by all its target customers in general. 2) Unwholesome Demand in unwholesome demand consumer badly wants the product but shouldnβt desire or take the decision to buy it. 3) Non-Existing Demand In non-existing demand also known as no demand, a marketer thinks that there is a demand for the product in the market but in reality, there is no demand for the product. 4) Latent Demand It is a consumer want that is unable to be satisfied. It can also be termed as the demand for which the product is not available or is not developed till now. 5) Declining Demand When a product demand starts declining with time, it is known as declining demand. 6) Irregular Demand When demand for a particular product is seasonal or time-based, it results in irregular demand. Such demands see both the extremes, the demand is either too high or too low. 7) Full Demand It is the best type of demand for any company as the company sees boon with this type of demand. It is the ideal situation, where supply=demand. It is also known as full market coverage. 8) Overfull Demand This demand is generated when there is a limited manufacturing/servicing capacity of the company for a product/service, but the demand for it is more than the capacity. It means that demand is more but supply is less.
- Ravi and Ramesh can do a job together in 20 days. They worked together for 12 days and then Suresh finished the remaining work alone in 10 days.Find how lo...
A and B can complete a work together in 24 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed ...
βPβ is 20% more efficient than βQβ. βPβ can do a piece of work in 15 days. They begin the work together, but βQβ leaves after 6 days. Th...
A, B, and C together can do a project in (64/7) days. B and C together need (96/9) days, and C alone completes half in 8 days. Fi...
βPβ and βQβ together can complete a work in 30 days. If βPβ increases his efficiency by 50% and βQβ decreases his efficiency by 50%, th...
A can finish a piece of work in 15 days and B can finish it in 20 days. They work together for 4 days and then B leaves. In how many more days can A alo...
Karan, Arjun and Krunal alone can complete a work in 50, 75 and 60 days respectively. All of them started working together but after 9 days from start K...
Efficiency of a man is 25% more than that of a woman. (2n + 4) men working 6 hours a day can complete a task in 15 days, whereas (3n - 2) women working ...
Choose the statements that correctly show two workers taking 6 hours and 9 hours to complete a task, respectively.
A buffalo alone can plough field βAβ in 40 days. A Bull alone can plough the field βAβ in 80 days. Find the number of days taken by 3 bulls and ...