Question

Using the Basic COCOMO model for an organic-type software project, the effort E (in person-months) is given by E = a × (KLO

  • C ^b, where a = 2.4 and b = 1.05. For an estimated project size of 20 KLOC, what is the approximate effort required?
A ≈ 48 person-months
B ≈ 24 person-months
C ≈ 20 person-months
D ≈ 56 person-months
E ≈ 100 person-months