Question

Using the Basic COCOMO model for an organic project (Effort = 2.4 × KLOC^1.05), what is the approximate effort required for a 10,000-line-of-code (10 KLO

  • C project?
A ≈10 person-months
B ≈24 person-months
C ≈2.4 person-months
D ≈100 person-months
E ≈27 person-months