Question
What is the maximum limit to the cost overrun arising on
account of extension in DCCO, being funded by a Standby Credit Facility, sanctioned at the time of initial financial closure of the project?Solution
In cases where lenders have specifically sanctioned a β Standby Credit Facility (SBCF) at the time of initial financial closure to fund cost overruns arising on account of extension in DCCO, they may fund cost overruns as per the agreed terms and conditions up to a maximum of 10% of the original project cost. However, in cases where SBCF was not sanctioned at the time of financial closure or sanctioned but not renewed subsequently, lenders may fund cost overruns arising on account of extension in DCCO as per the agreed terms and conditions, up to a maximum of 10% of the original project cost (excluding IDC), provided the additional funding shall be priced at a premium to what would have been applicable on a pre-sanctioned SBCF. Lenders shall ensure that the loan-contracts shall ab-initio specify the additional risk premium to be charged on such SBCF, which may be revised upwards based on actual risk assessment at the time of sanction of such facilities. The additional risk premium shall be subject to a floor of 1.00 per cent .
The ratio of efficiencies of X and Y for doing a certain work is 5 βΆ 9. Working together, they can complete a work in 15 days. X alone will complete 6...
βPβ alone can do 60% of a work in 18 days and βQβ alone can do 30% of the same work in 9 days. βPβ, βQβ and βRβ together can finish ...
- If Rina can complete a project in 36 days by working 9 hours a day, how many hours per day should she work to complete the project in 18 days?
A can do a job alone in 66 days, B can do it alone in 55 days, while A, B, and C working together can complete the job in 11 days. In how many days can ...
A can complete a piece of work in 24 days. He worked for 21 days and then B finished the remaining work in 6 days. In how many days can A and B finish t...
A, B, and C together wrap up a task in 14 days. B and C together can finish it in (280/18) days, and C alone completes half in 14 days. Find the ratio o...
- If Priya takes five times the time that Kabir takes or six times the time that Aarav takes to finish a task, and all three working together can complete it...
28 men can complete a work in 20 days. 40 women can complete the same work in 28 days. 20 men and 12 women started working and after 16 days, 20 more wo...
Gagan can do a piece of work in 14 days. Magan is 40% more efficient than Gagan. How many days will Magan and Gagan together complete the work?
A man, a woman, a boy, and a girl can complete a certain task individually in 84 days, 105 days, 140 days, and 210 days respectively. How long will it t...