Question
βPβ alone can do 60% of a work in 18 days and
βQβ alone can do 30% of the same work in 9 days. βPβ, βQβ and βRβ together can finish the work in 10 days. The efficiency of βQβ is what percent of the efficiency of βRβ?Solution
ATQ, βPβ alone can do the complete work in (18/60) Γ 100 = 30 days βQβ alone can do the complete work in (9/30) Γ 100 = 30 days Let total work = 300 units Pβs efficiency = 300/30 = 10 units per day Qβs efficiency = 300/30 = 10 units per day P, Q and Rβs efficiency = 300/10 = 30 units per day Rβs efficiency = 30 β 10 β 10 = 10 units per day Required percentage = (10/10) Γ 100 = 100%
When was the World Bank established?
Which bank has become the first to officially introduce the Mahila Samman Savings Certificate (MSSC) scheme?Β
Where did the 36th National Games take place in September β October 2022?
Which type of banks are allowed to participate in government related business?
Which one of the following is provided under the Third Schedule of the Factories Act, 1948?
Which of the following personalities was conferred with the βPadma Vibhushanβ award?Β
Business, commerce and movement within India are described as part of the Constitution?
______ drains into Arabian sea.
In a volleyball game, each team comprise of how many players?
Β To reduce a bankβs risks on confirmations and negotiations of irrevocable letters is called?