options. Fill in the blank with appropriate words from the options. Russian President Vladimir Putin’s visit to New Delhi for the 21st India-Russia Summit meeting with Prime Minister Narendra Modi highlights the __________ (1) efforts by both leaders to nurture and to provide further ______________ (2) to the ‘India-Russia Special and Privileged Strategic Partnership’. In the new grammar of multipolarity and globalisation, it is of ___________ (3) importance for dependable partners to ensure ____________ (4) sensitivity to their mutual interests. More importantly, the robust partnership between India and Russia has come out of the ______________ (5) of the Cold War inheritance. A practical and result-oriented approach will pave the way for the most ____________ (6) partnership. The Putin-Modi meeting in an atmosphere of ______________ (7) regional and global transformations can ensure not only a new lease of life but can also generate more vitality to this trustworthy camaraderie.Solution
Here, ‘constant’ is the correct form of word to be used.
X and Y together can complete 30% of a work in 12 days while Y alone takes 100% more time than X and Y together to finish the whole work. Find the time ...
36 women can complete a task in 20 days. If 18 women start the task and after 15 days ‘y’ more women join, ensuring the remaining work is completed ...
- 'Rahul', 'Amit', and 'Vikram' together can complete a work in 20 days. 'Rahul' and 'Amit' together can complete the same work in 60 days. 'Vikram' alone ca...
‘P’, ‘Q’ and ‘R’ can finish a task in 12 days, 36 days and 72 days respectively. ‘P’ and ‘Q’ begin the task. After ‘n’ days, ‘...
- A man completes a work in 16 days. A woman finishes half of that work in 10 days. How many days will they take together to finish 75% of the work?
12 man can make a wall in 5 days. How many men required to complete the same work in 6 days ?
- Two workers, A and B, can finish a task in 36 days and 48 days respectively, working alone. How many days will they take to complete the work together?
Workers A and B can finish a task in 30 days when working together. They worked for 18 days, and then C completed the rest of the task alone in 12 days....
Leela and Laila, working together, can complete a task in 18 days. Given that Laila is 125% more efficient than Leela, how long would it take for Laila ...
A, B, and C can complete a task individually in 45, 35, and 63 days respectively. They start working together, but A leaves 24 days before the work is c...