15 male employees or 20 female employees of a company can complete a project in 26 days. How long will 30 male employees and 12 female employees togethe...
A and B can finish a work working on alternate days in 19 days, when A works on the 1st day. Similarly, they can finish the work working on alternate da...
A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 12 days, and C alone in 24 days, in wha...
The total age of 'R' and 'D' eight years ago was thirty-six. Four years separate 'R' and 'D' in age. Determine the sum of total age (in years) between '...
If 12 persons working 12 hours a day dig 12 meters of a tunnel in 12 days how many men are required to dig additional 4 meter of the tunnel (of the same...
A motorboat whose speed is 20 km/h in still water takes 30 minutes more to go 24 km upstream than to cover the same distance downstream. If the speed of...
In a 200 m race, P beats Q by 35 m or 7 seconds. What is P's time over the course?
A and B can complete a task in 25 days. B alone can complete 33 1/3 % of the same task in 15 days. In how many days can A alone complete 4/15th
A trip from Mumbai to Pune takes 4 hours 30 minutes at a speed of 60 km/hr. How long (in hours) will it take to complete, if the speed is 15m/sec?
3 men dig a hole in 10 days. How many days would it take for 5 men to dig the same hole ?