Question
Which among the following pair sits at the
ends? Directions: Answer the questions based on the information given below. Six persons P, Q, R, S, T, and U are sitting in a row such that all are facing towards the north direction. U sits third to the right of T. One person sits between T and P. Two persons sit between P and Q. One person sits between Q and R, who sits third left of S. S sits on the right of U.Solution
U sits third to the right of T. One person sits between T and P. P ___ T ____ ____ U …. (I) T ____ P U ……. (II) Two persons sit between P and Q. One person sits between Q and R, who sits third left of S. S sits on the right of U. P R T Q S U …. (I) Q  T   R  P U S ……. (II) Final arrangement as show below: Q        T         R        P        U        S
A and B can finish a task together in '2t' days. B alone can complete the task in 10 days, while A alone can do it in '5t' days. Find the value of 't'.
A takes 30% longer to complete a task than B. If the total payment for the work is Rs. 11,500 and they complete the task together, how much should A be ...
Bittu can finish a task by himself in 60 days, while Anoop and Bittu working together can complete the same task in 28 days. If A...
28 men can complete a work in 20 days. 40 women can complete the same work in 28 days. 20 men and 12 women started working and after 16 days, 20 more wo...
A can fabricate a divider in 15 days , while B alone can assemble it in 25 days, If they construct it together and get an installment of Rs 7000, then f...
‘A’ is 50% less productive compared to ‘B’, who is 20% more productive than ‘C’. Together, they can finish a task in 36 days. After ‘B’...
Aman manages to write 256 pages of a book over a span of 24 days, dedicating 8 hours each day to this task. Meanwhile, Pranav, who is known to be 50% mo...
- Varun and Arnav can finish a work in 28 days and 56 days respectively when working alone. Varun starts first. In how many days should Arnav join him so tha...
132 unit of work can be completed by P alone in 22 days. P started working alone and joined by Q after 10 days such that they completed the remaining wo...
Working alone, 'C' can complete a job in 30 days. 'D' takes 20% less time than 'C' to finish the same job. Calculate the percentage of work done by 'C' ...