Question
What is the position of the box with banana?
Answer the questions based on the information given below. Seven boxes viz. K, L, M, N, O, P and Q are filled with different fruits viz. Apple, Banana, Guava, Grapes, Orange, Mango and Kiwi are kept one above another in a stack. The box kept at the lowermost position is numbered as 1 and the box kept at the topmost position is numbered as 7. Box P is kept four boxes above the box with mango where the box with orange is kept exactly in the middle between them. Only two boxes are kept between the box with orange and box O which is not kept at the topmost position. As many boxes kept above box O as below the box with Kiwi which is kept two boxes away from box N. Box Q with grapes is kept at an odd numbered position. Box M is kept immediately above the box with banana and two boxes below box L. The box with apple is kept immediately below the box with guava.Solution
Box P is kept four boxes above the box with mango where the box with orange is kept exactly in the middle between them. Only two boxes are kept between the box with orange and box O which is not kept at the topmost position. As many boxes kept above box O as below the box with Kiwi which is kept two boxes away from box N. Box Q with grapes is kept at an odd numbered position.
Box M is kept immediately above the box with banana and two boxes below box L. The box with apple is kept immediately below the box with guava. Hence, cases 1 and 3 get eliminated.
So final arrangement-
- Ayaan and Kabir started working together on a task. Ayaan does 4 units per day and Kabir can finish the full task in 25 days alone. The total work is 100 u...
A and B can complete a work together in 24 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed ...
A can complete `1/4` of a work in 6 days and B can complete `2/5` of the work in 12 days. In how many days can both A and B together complete the work?<...
A and B can complete a work in 12 days and 16 days, respectively. They start working together, but after 4 days, A leaves the work. C joins B, and they ...
Atul, Qureshi, and Chintu can individually complete a certain task in 27 days, 30 days, and 36 days, respectively. They all begin working on the task to...
'K' and 'L' together can complete a work in 24 days. They started working together but after 16 days, 'L' left and remaining work was completed by 'K' a...
25 men can complete a piece of work in 13 days. One man starts the work and after every day one more man joins the work and this continues till the work...
P can complete a job in 30 days. Q alone can complete the same job in 20 days. P works for 18 days and then the remaining job is completed by Q. How man...
A can complete a task in 20 days, and B can complete it in 25 days. When B and C collaborate, they can finish the same task in 75/8 days. Now, if A and ...
Amit and BK working together can finish a particular task in 90 days, while BK and Chiku working together can complete the same task in 70 days. Determi...