Question
How many triangles are there in the figure?
src="http://ixambee.com/questionimage/ssc/SSC-MT7-E-17.jpg" alt="" width="355" height="160" />Solution
The triangles are : ABI, AHI, ABH, BJI, HJI, JBH, JBC, JHG, CJK, GKJ, KCD, KGF, KDF, DLE, FLE, EDF, DLK, FLK, BHG, BHC, CHF, GBD, DFC, DFG, BAJ, HAJ, DKE, FKE.
- βPβ and βQβ together can finish a task in 15 days while βQβ alone can do it in 25 days. If the ratio of efficiencies of βPβ and βRβ is ...
A man, a woman and a boy can do a work in 3, 2, 6 days respectively. How many children were required with 1 man and 1 woman to complete the same work in...
X can do a piece of work in 33 days. He worked at it for 3 days and then Y finished it in 20 days. In how many days can X and Y together finish the work?
Working alone, 'C' can complete a job in 30 days. 'D' takes 20% less time than 'C' to finish the same job. Calculate the percentage of work done by 'C' ...
A 40 hectare field is reaped by 4 men, 6 women and 8 children together in 10 days. If working capabilities of a Man, a Woman and a Child are in the rati...
Naina and Kalpana working together can do a piece of work in 10 days, whereas Naina alone can do it in 12 days. In how many days can Kalpana do it alone?
30 workers putting in 8 hours a day finish a task in 10 days. How many days will it take for 20 workers working 12 hours daily to finish the same task?
Amit manages to reach 25% of a sales goal in 6 days, whereas Geeta can achieve 40% of the same goal within the same timeframe. How long would it take fo...
P can do a piece of work in 12 days, Q can complete double the work in 20 days and R can do the work in 15 days. If all of them together earn Rs. 2500, ...
- E and F can complete a task in 24 days together. E alone can do it in 40 days. Find the time F alone would take.