Question
 OXTJIL
Directions (Q.96-100): In each question below is given a group of letters followed by four combinations of digits/symbols numbered (1), (2), (3) and (4). You have to find out which of the four combinations correctly represents the group of letters based on the following coding system and the conditions that follow and mark the number of that combination as your answer. If none of the combinations correctly represents the group of letters, mark (5) i.e. ‘None of these’ as your answer. Conditions: (i) If the first letter is a consonant and the last letter is a vowel, their codes are to be interchanged. (ii) If both the first and the third letters are consonants, both are to be coded as ‘T’. (iii) If the first letter is a vowel and the last letter is a consonant, both are to be coded as the code for the consonant.Solution
Condition III applies: OÂ Â Â Â Â Â Â Â Â Â Â Â XÂ Â Â Â Â Â Â Â Â Â Â Â TÂ Â Â Â Â Â Â Â Â Â Â Â Â JÂ Â Â Â Â Â Â Â Â Â Â Â Â IÂ Â Â Â Â Â Â Â Â Â Â Â Â Â L 5Â Â Â Â Â Â Â Â Â Â Â Â Â 8Â Â Â Â Â Â Â Â Â Â Â Â Â $Â Â Â Â Â Â Â Â Â Â Â Â Â 9Â Â Â Â Â Â Â Â Â Â Â Â Â &Â Â Â Â Â Â Â Â Â Â Â Â 5
Work efficiency of Chacha and Bhatija are in the ratio of 3 : 1. They working together to do a piece of work and completed the work in 24 days. Now in h...
A certain number of men, represented as 'm', can finish a task in 40 days. However, if there were 15 additional men, the same task would be completed in...
- Working 6 hours a day, Rahul can complete a work in 25 days. How many hours a day should he work to complete the same work in 15 days?
A2 type ‘P’ pipes can fill a tank in 350 hours, while B2 type ‘Q’ pipes can fill the same tank in 504 hours. (10A × 6B) t...
A started a work such that he can complete the whole work in 30 hours. After working for 10 hours, he worked with the rate such that the whole work can ...
4 girls together are as efficient as one man. If 32 girls can complete 40 garments in 5 days, how many men are needed to complete the same work in 2 days?
V and N, working individually, can complete a task in (w – 2) days and (w + 4) days, respectively. N initiated the task alone and was later joined by ...
A and B together can finish a job in ‘x’ days, while A alone takes ‘x + 32’ days to complete it. B alone can finish the job in 90 days. If C is ...
- Pipes A and B can fill a cistern in 48 and 80 minutes respectively. Another pipe C can empty the cistern in 1 hour 36 minutes. A and C are opened first. Af...
'C' can complete a work in 18 days whereas 'D' can do the same work in 30 days.They started working together but 'C' worked with 60% of his efficiency w...