A and B together can do a piece of work in 30 days, B
and C together can do it in 20 days. A starts the work and works on it for 5 days, then B takes it up and works for 15 days. Finally, C finishes the work in 18 days. In how many days can C do the work when doing it separately (in days)?Solution
(A + B)’s 1 day work = 1/30 And (B + C)’s 1 day work = 1/20 Also, A’s 5 days w + B’s 15 days w + C’s 18 days w = 1 work ⇒ A’s 5 days w + B’s 5 days w + B’s 10 days w + C’s 10 day w + C’s 8 day w = 1 work ⇒ (A + B)’s 5 days w + (B + C)’s 10 days w + C’s 8 days work = 1 work ⇒ 5/30 + 10/20 + C’s 8 days work = 1 work ⇒ 1/6 + 1/2 + C’s 8 days work = 1 work ⇒ C’s 8 days work = 1 – ( 1/6 + 1/2 ) work ⇒ C’s 8 days work = 1 – ((1 + 3)/6) = 1 - 4/6 = 1 - 2/3 ∴ C’s 8 days w = 1/3 work ∴ C will complete the work in 8 × 3 = 24 days
The term Fire Ice is used for ___?
What term is used for atoms that have the same number of protons but different numbers of neutrons?
Which of the following is the sweetest sugar?
Which acid is majorly found in Orange?
What is the total number of carbon atoms in a molecule of butane?
The substance that is added to make natural rubber strong and more bouncy is-
Which vitamin is water-soluble?
Which gas is primarily monitored to assess organic pollution in sewage and surface water?
What is the atomicity of Helium?
What causes the black color of Black Soil?