Question
‘P’ who is 20% more efficient than ‘Q’ can finish a work in 15 days. ‘P’ and ‘Q’ start working together, but ‘Q’ leaves after 6 days. The remaining work is completed by ‘P’ alone in ‘y’ days. Find the value of ‘y’.
More Quant Miscellaneous Questions
- The bar graph given below shows the number of JK Tyres manufactured by a Showroom on five different days. Read the graph carefully and answer the question ...
- A merchant has two types of sugar. Type A costs 50 per kg, and Type B costs 70 per kg. In what ratio should the two types be mixed to get a mixture that co...
- An investor buys 240 shares of face value ₹10 each at ₹160 per share. The broker charges 1% brokerage on the purchase. The company declares a 250% dividend...
- Question 4
- The shortest distance between skew lines can be found using:
- Calculate Tina's age five years ago given that the current average age of Tina, Rohan, and Ramu is 25 years, while the average age of Rohan and Ramu alone ...
- From a point 30 m away from the base of a building, the angle of elevation to the top of the building is 60°. Find the height of the building.
- If x2 - 7x + 1 = 0, then find the value of: 3 + ( x 6 + x 4 + x 2 + 1)/ 7x 3
- If sets A and B contain 4 and 5 elements respectively, then the total number of binary relations from A to B is:
- If 6x - 3y = 9, and 9xy = 18, then what is the value of 6x + 3y?
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)