Question
A group of 36 boys works 13 hours per day and completes
37.5% of a task in 20 days. After these 20 days, 'X' boys leave the job. The remaining boys continue the work, now putting in 15 hours per day, and finish the rest of the task in 52 days. If a team of (5X) boys works 12 hours per day, how many days will they take to complete the entire task on their own?Solution
ATQ,
36 * 13 * 20/(37.5/100) = (36 – X) * 15 * 52/((100 – 37.5)/100)
12 * 8/3 = (36 – X) * 100/62.5
X = 36 – 20 = 16
Let the number of days in which 5X boys complete the whole work be 'n' days.
36 * 13 * 20/(37.5/100) = (5 * 16) * 12 * n
n = 26
Which one of the following is not the component of PM Virasat ka Samvardhan (PM VIKAS) Yojana?
What is India’s Rank in Human Capital Index 2020?
Under Budget 2025–26, which measure best exemplifies horizontal fiscal equity between Centre and States?
What is the main goal of the Indo-Pacific Economic Framework for Prosperity (IPEF)?
Which of the following SDGs has shown the most substantial improvement in the SDG India Index 2023-24?
What is the primary aim of the LAQSHYA programme?
Consider the following Statements and choose the option with wrong Statements.
(i) International Financial Services Centres Authority is constitu...
According to the Economic Survey 2024–25, India’s real GDP growth projection for FY26 lies between:
What is the primary reason for the expansion of BRICS membership to include new countries?
The Ujjwala 2.0 scheme provides how many free LPG refills to eligible beneficiaries?