Question
βPβ, βQβ, and βRβ can
complete a task in 10 days, 15 days, and 20 days, respectively. βPβ starts the task alone and is joined by βQβ on the second day. On the third day, βQβ is replaced by βRβ, and again on the fourth day, βPβ works alone. The process repeats in the same manner. Find the total time taken to complete the task. (Round off to two decimal places)Solution
ATQ,
Let the total work be the LCM of [10, 15, 20] = 60 units. Efficiency of βPβ = 60/10 = 6 units/day. Efficiency of βQβ = 60/15 = 4 units/day. Efficiency of βRβ = 60/20 = 3 units/day. Work done on the first day = 6 Γ 1 = 6 units. Work done on the second day = (6 + 4) Γ 1 = 10 units. Work done on the third day = (6 + 3) Γ 1 = 9 units. Total work done in the first three days = 6 + 10 + 9 = 25 units. Remaining work = 60 β 25 = 35 units. Time taken to complete the remaining work = (6/6) + (10/10) + (9/9) + (10/17) β 3 + (10/17) β 3.59 days. Total time = 3 + 3.59 = 6.59 days.
25% of the work done by Arjun in 6 days equals 50% of the work done by Karan in 3 days. If Arjun alone finishes the full work in 24 days, find the time ...
12 man can make a wall in 5 days. How many men required to complete the same work in 6 days ?
Vijay can do a piece of work in 16 days and Sanjay can do the same work in 24 days. If Vijay works for 6 days and got Rs. 2700, and the remaining work w...
- E and F can complete a task in 24 days together. E alone can do it in 40 days. Find the time F alone would take.
A and B together can complete a work in 12 days. B and C together can complete the same work in 15 days, and A and C together in 20 days. If they all wo...
B is 20% more efficient than A. If B was 60% more efficient than A, then, B could complete the work in 18 days lesser than days taken by A. What fractio...
βPβ and βQβ can complete a task in 72 days, while βQβ and βRβ can finish 60% of the same task in 27 days. If βRβ is twice as efficie...
Rohit and Karan can complete a work alone in 64 days and 80 days respectively. Working together they earn Rs. 7,200. How much does Karan get?
35 people working 7 hours a day take 22 days to complete a task. How many people working for 6 hours a day are needed to complete five times the given t...
A and B together can do a piece of work in (p-8.8) days.The efficiency of D is 10% less than the efficiency of B. A and C together can do the same piece...