Question
Mukta takes 8 hours less than Raj to complete the work,
and Mukta also takes 32 hours less than Bheem to complete the same work. If Raj and Bheem start working together and the time taken by them to complete the work is same as the time taken by Mukta alone to complete the work, then what will be the time taken by Mukta and Bheem to complete the given work.Solution
Let the number of days taken by Mukta to complete the work be “x”. Number of days taken by Raj = (x + 8) Number of days taken by Bheem = (x + 32) 1/(x + 8) + 1/(x + 32) = 1/x 2x2 + 40x = x2 + 40x + 256 2x2 - x2  = 256 x2  = 256 or x = 16 Number of days taken by Mukta = 16 days Number of days taken by Bheem = 48 days Let the total work be 48 units. Mukta’s one-day work = 3 units Bheem’s one-day work = 1 unit Required time = 48/4 = 12 days

Which of the given figures when placed in the 5th position would continue the series that is established by the first four figures?
Select the figure from the alternatives which will complete the pattern in given question figure.
Read the given statements and conclusions carefully. Assuming that the information given in the statements is true, even if it appears to be at varianc...
If the word 'EXAMINATION' is arranged in alphabetical order from the right end, then which of the following letter will be fourth letter to the right of...

Which figure should replace the question mark (?) if the series were to continue?


In each of the following questions, find out which of the answer figures can be formed from the pieces given in the problem figure.