Question
12 men take 6 days to complete a piece of work. They
worked for a period of 2 days. After that, they were joined by 4 more men. How many more days will be taken by them to complete the remaining work?Solution
12 men = 6 days Work done by 12 men in one day = 1/6 Work done by 12 men in 2 days = 1/6 × 2 = 1/3 Remaining work = 1 - 1/3 = 2/3 Now, 4 men joined them Therefore, 2/3 rd of work is done by 16 men in x days We have the formula, M1 × D1 / W1 = M2 × D2 / W2 Here, M1 = 12, D1 = 2 and W1 = 1/3 M2 = 16, D2 = x and W2 = 2/3 (12 × 2)/(1/3) = (16 × x )/(2/3 ) x = 3 days ALTERNATE SHORTCUT METHOD M1 × D1 = M2 × D2 12× 6 = 12× 2 +(12+4) × x 72 = 24 +16 x 48 = 16 x So x=3days
The sum of three positive numbers is 18 and their product is 162. If the sum of two numbers is equal to the third then the sum of squares of the numbers is
In an examination 73%of the candidates passed in quantitative aptitude test, 70% passed in General awareness and 64% passed in both. If 6300 failed in b...
`2/5` ___Â 15 ___Â 115___ 20 ___Â 4 = 581
If a dozen apples weigh 1.8 kg in total, how many apples will be there in 3 boxes weighing 23.250 kg each?
The daily wages of A and B respectively are Rs.3.50 and 2.50. When A finishes a certain work, he gets a total wage of Rs. 63. When B does the same work,...
Economy of a bowler after (0.5n – 6) overs is 6. In the next six overs, he conceded 12, 9, 18, 7, 20 and 10, and his economy increases by 2. Find the ...
160 cycles were sold for Rs.524,000 resulting in a loss of 10%. What was the cost price of a cycle (in Rs.)? (rounded off to the nearest rupee)
906 ___Â 6 ___Â `sqrt1225` Â ___Â 500 ___Â 850 = 4,935
69,012 ___Â 20,167 ___Â 51,246 ___Â 6 ___Â 50,000 = 7,386
Rs.2420 were divided among A, B, C so that A: B=5 : 4 and B : C = 9 : 10 then C gets