12 men take 6 days to complete a piece of work. They worked for a period of 2 days. After that, they were joined by 4 more men. How many more days will be taken by them to complete the remaining work?
12 men = 6 days Work done by 12 men in one day = 1/6 Work done by 12 men in 2 days = 1/6 × 2 = 1/3 Remaining work = 1 - 1/3 = 2/3 Now, 4 men joined them Therefore, 2/3 rd of work is done by 16 men in x days We have the formula, M1 × D1 / W1 = M2 × D2 / W2 Here, M1 = 12, D1 = 2 and W1 = 1/3 M2 = 16, D2 = x and W2 = 2/3 (12 × 2)/(1/3) = (16 × x )/(2/3 ) x = 3 days ALTERNATE SHORTCUT METHOD M1 × D1 = M2 × D2 12× 6 = 12× 2 +(12+4) × x 72 = 24 +16 x 48 = 16 x So x=3days
'A' and 'B' together can do some work in 15 days. 'A' however is 30% more efficient than 'B'. If 'A' and 'B' started the work alone but 'A' left after w...
Amit and Binod receive Rs.1400 for work of 7 days. If Amit is 4 times efficient than Binod, then find the daily wage received by Binod.
Virat can do a piece of work in 28 days and Sachin can do the same work in 42 days. If Virat works for 4 days and got Rs. 1800, and the remaining work w...
Anil and Ashish receive Rs.2200 for work of 8 days. If Anil is 4 times efficient than Ashish, then find the daily wage received by Ashish.
A team of 32 men and 28 women can complete a task in 60 days. When an additional eight men join the team, they are able to finish (4/5) of the same task...
Karan, Arjun and Krunal alone can complete a work in 40, 60 and 48 days respectively. All of them started working together but after 3 days from start K...
M and N, working in tandem, can successfully attain the sales target within a span of 15 days. Now, if N's efficiency is _______ percent less than that ...
'B' and 'C' in a team can complete a piece of work in 25 days and on other hand 'B' alone can do the same work in 40 days. If they started the work in...
P and Q can complete a work in 20 days and 30 days, respectively. P, Q and R together can complete the work in 10 days. If R get a total wage of Rs. 480...
A work can be completed by ‘A’ and ‘B’, alone in 10 days and 15 days, respectively. Find the number of days taken by ‘C’ to complete the sam...