Question
βAβ and βBβ can do a piece of work in 25 days
and 30 days, respectively. If they started the work together and worked on it for 5 days, then find the time taken by βBβ alone to complete the remaining work.Solution
Let total amount of work be 150 units (LCM of 25 and 30). Efficiency of βAβ = 150/25 = 6 units/day Efficiency of βBβ = 150/30 = 5 units/day Amount of work done by βAβ and βBβ together in 5 days = (6 + 5) Γ 5 = 55 units Time taken by B to complete remaining work = (150 β 55)/5 = 19 days
The book titled 'Every Vote Counts - The Story of Indiaβs Electionsβ was written by ______.
When was Project Tiger started in India?
Which book was NOT written by Munshi Premchand?
Recently which country’s central bank has signed a MoU with RBI to expand cooperation in anti-money laundering and combating the financing of terr...
The book 'Target 3 Billion' is written by ______.
Odometer is used to measure what?
Cyclones Gulab was a tropical cyclone that caused considerable damage to ______ Asia.
Which Indian author wrote the book βThe English Teacher β?
Who authored the novel "Khasakkinte Itihasam"?
Who authored "Satyarth Prakash"?