📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!


    Question

    Time taken by 'A', 'B' and 'C' to complete a work is 51

    days, 85 days and 102 days respectively. All of them started the work together but 'B' and 'A' left the work 19 days and 9 days respectively before the completion of work. Find the total time taken to complete the work.
    A 34 days Correct Answer Incorrect Answer
    B 26 days Correct Answer Incorrect Answer
    C 14 days Correct Answer Incorrect Answer
    D 25 days Correct Answer Incorrect Answer

    Solution

    Let the total work be 510 units (LCM of 51, 85 and 102) Efficiency of 'A' = (510/51) = 10 units/day Efficiency of 'B' = (510/85) = 6 units/day Efficiency of 'C' = (510/102) = 5 units/day Let the time taken to complete the work be 'n' days. So, (10 + 6 + 5) X (n - 19) + (10 + 5) X 10 + 5 X 9 = 510 Or, 21n - 399 + 150 + 45 = 510 Or, 21n = 714 Or, 'n' = 34

    Practice Next
    ask-question