Question
A can do a piece of work in 12 days, while B alone can do it in 18 days. They work together for 6 days and the rest of the work is completed by C in 4 days. If they get Rs. 720 for the whole work, how should they divide the money?
More Time and work Questions
- 'A' alone can do 40% of a work in 12 days and 'B' alone can do 50% of a work in 10 days. 'B' and 'C' start working together and work for 6 days, and the re...
- A is half as efficient as B. C does half as much work as A and B together. If c alone can do the work in 40 days. Then in how many days will A, B and C tog...
- Anil and Ashish receive Rs.2000 for work of 10 days. If Anil is 4 times efficient than Ashish, then find the daily wage received by Ashish.
- A can complete a work in 20 days and B can complete it in 30 days. They work together for 6 days, then B leaves. In how many total days will the work be co...
- Aman and Rohan can finish a job alone in 12 days and 30 days respectively. Aman began the task alone. After how many days should Rohan join him so that the...
- ‘M’ is 60% more efficient than ‘N’. ‘N’ started the work alone and worked for 16 days and after that ‘N’ is replaced by ‘M’. If the total work is completed...
- A and B can complete a work together in 20 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by B alone in 6...
- 'Sita' can complete some work alone in 20 days. 'Geeta' is twice as efficient as 'Reeta' and three times as efficient as 'Sita'. If 'Sita' and 'Reeta' star...
- A and B can jointly finish a task in 42 days, while B and C together take 35 days to finish the same task. If B can finish the task alone in 105 days, how ...
- If 12 men working 12 hours a day can make 12 quilts in 12 days, then in how many days 24 men working 24 hours per day will make 24 quilts?
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)