Question
A can do a piece of work in 12 days, while B alone can
do it in 18 days. They work together for 6 days and the rest of the work is completed by C in 4 days. If they get Rs. 720 for the whole work, how should they divide the money?Solution
Work done by A and B in 6 days = {(1)/(12) + (1)/(18)} x 6 = (5)/(6) Work remaining = 1 - (5/6) = (1/6) C alone can do the work in 6 x 4 = 24 days Ratio of their share work = (6/12) : (6/18) : (4/24) = 3:2:1 Share of A’s wages = (3/6) x 720 = Rs. 360 Share of B’s wages = (2/6) x 720 = Rs. 240 Share of C’s wages = (1/6) x 720 = Rs. 120
What will be the difference between the marks secured by E and D?
Who among the following manufacture biscuits?
Statement: Â Â Â Â
 Only a few Gold are Silver         Â
Only a few Gold are Diamond     Â
Conclusion:    �...
Four of the following five are alike in certain way based from a group, find the one that does not belong to that group?
Which of the following statements is/are true?
How many persons play between R and U?
Who among the following person was born in the same month along with B?
How many boxes are kept above the one that contains Papaya?
How many floors are there above G’s floor?
Who among the following attends conference in Bhutan and in which day?