Question
A can complete a piece of work in 12 days, and B can
complete the same work in 16 days. They work together for 4 days, and then A leaves. How many more days will B take to finish the remaining work?Solution
Work done by A in 1 day = 1/12, Work done by B in 1 day = 1/16 Work done by A and B together in 1 day = (1/12) + (1/16) Taking LCM of 12 and 16 = 48, Work done together = (4/48) + (3/48) = 7/48 Work done in 4 days = 4 × (7/48) = 28/48 = 7/12 Remaining work = 1 - 7/12 = 5/12 B's work rate = 1/16 Time taken by B = (5/12) ÷ (1/16) = (5/12) × 16 = 20/3 = 6.67 days. Correct Option: c) 6.67 days


In the question, if a mirror is placed on the line AB then which of the answer figures is the right image of the given figure?
Question figur...
Identify the mirror image of the following figure when the mirror is placed to the right of the figure.

Select the correct mirror image of the given combination when the mirror is placed at ‘XX’ as shown.
Choose the alternative which is closely resembles the water-image of the given combination.
Select the correct mirror image of the given combination when the mirror is placed at line AB as shown.
Select the correct mirror image of the given figure when the mirror is placed to the left of the figure.
Select the correct mirror image of the given figure when the mirror is placed to the right of the figure.