      'V' can complete (1/2) of a project in 30 days, and 'V'

      along with 'W' can complete the entire project in 20 days. Determine the time 'W' requires to complete 75% of the project alone.
      A 12.8 days Correct Answer Incorrect Answer
      B 10.2 days Correct Answer Incorrect Answer
      C 22.5 days Correct Answer Incorrect Answer
      D 19.6 days Correct Answer Incorrect Answer

      Solution

      ATQ, Time taken by 'V' to complete the whole job alone = 30Γ—2=60 days Let the total amount of work = LCM of 60 and 20 = 60 units Efficiency of 'V' =60/60 = 1 units per day Efficiency of (V + W) = 60/20= 3 units per day Efficiency of 'W' = 3βˆ’1 = 2 units per day Desired time = (0.75 Γ— 60/2) = 22.5 days