Question

'V' can complete (1/2) of a project in 30 days, and 'V' along with 'W' can complete the entire project in 20 days. Determine the time 'W' requires to complete 75% of the project alone.

A 12.8 days
B 10.2 days
C 22.5 days
D 19.6 days