πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!


    Question

    In the question, two Quantities I and II are given. You

    have to solve both the Quantity to establish the correct relation between Quantity-I and Quantity-II and choose the correct option. Bhuvan alone can complete a task in 11.25 days. Anuj and Bhuvan together can complete the same task in 5 days. Charu alone can complete 20% of the same task in 3.6 days. Quantity I: Amount of work completed by Anuj alone in 4 days. Quantity II: Amount of work completed by Bhuvan and Charu together in 3 days.
    A Quantity I > Quantity II Correct Answer Incorrect Answer
    B Quantity I < Quantity II Correct Answer Incorrect Answer
    C Quantity I β‰₯ Quantity II Correct Answer Incorrect Answer
    D Quantity I ≀ Quantity II Correct Answer Incorrect Answer
    E Quantity I = Quantity II or No relation can be established Correct Answer Incorrect Answer

    Solution

    ATQ, Let Anuj, Bhuvan and Charu be defined as A, B and C. Let the total work = 90 units (L.C.M of 11.25 and 3.6) Then, the efficiency of β€˜B’ = 90 Γ· 11.25 = 8 units/day The combined efficiency of β€˜A’ and β€˜B’ = 90 Γ· 5 = 18 units/day So, the efficiency of β€˜A’ = 18 – 8 = 10 units/day Number of days taken by β€˜C’ alone to complete the entire work = 3.6 Γ— 5 = 18 days Therefore, the efficiency of β€˜C’ alone = 90 Γ· 18 = 5 units/day Quantity I: Work done by β€˜A’ alone in 4 days = 10 Γ— 4 = 40 units So, Quantity I = 40 units Quantity II: Work done by β€˜B’ and β€˜C’ together in 3 days = (8 + 5) Γ— 3 = 39 units So, Quantity II = 39 units Therefore, Quantity I > Quantity II

    Practice Next
    More Quantity Inequality Questions

    Relevant for Exams:

    ask-question

    Not sure which exam is best for you Talk to our expert

    Get My Free Call