Question
Quantity I: A bag contains 5
identical gold coins, and the number of ways in which 'p' coins can be drawn from the bag is 10. Determine the value of 'q', given that q = p+2p+3 (with p>0). Quantity II: Two people, Ajay and Vijay, can together complete a task in 11.25 days. The ratio of their efficiencies is 3:5 (it is not specified who is more efficient). Calculate the time (in days) taken by Ajay alone to finish the work. In the question, two quantities I and II are given. You have to solve both the quantities to establish the correct relation between Quantity-I and Quantity-II and choose the correct option.Solution
ATQ, Quantity I: Total coins in the bag = 5 Total number of coins which are withdrawn from the bag = βpβ Number of ways in which βpβ coins can be drawn from the bag = 5Cp = 10 5!/p!(5-p)!=10 120/p!(5-p)!=10 p! (5 β p)! = 12 Maximum value βpβ can take is 5. When p = 1, then p! (5 β p)! = 1! (5 β 1)! = 24 When p = 2, then p! (5 β p)! = 2! (5 β 2)! = 12 When p = 3, then p! (5 β p)! = 3! (5 β 3)! = 12 When p = 4, then p! (5 β p)! = 4! (5 β 4)! = 24 When p = 5, then p! (5 β p)! = 5! (5 β 5)! = 1 Hence, possible values of βpβ = 2 and 3. Now, q = p + 2p + 3 = 11 (when p = 2) and 18 (when p = 3) Hence, possible values of y are 11 and 18. Quantity II: Case 1: When Ajay is more efficient than Vijay. Ratio of efficiency of time taken by Ajay to Vijay is 5: 3. Let time taken Ajay and Vijay alone to finish the work is β3pβ days and β5pβ days respectively. According to the question: 1/3p+1/5p=1/11.25=4/45 (5+3)/15p=4/45 p = 6 Time taken by Ajay alone to finish the task = 3p = 18 days Case 2: When Ajay is less efficient than Vijay. Ratio of efficiency of time taken by Ajay to Vijay is 3: 5. Let time taken Ajay and Vijay alone to finish the work is β5pβ days and β3pβ days respectively. According to the question: 1/5p+1/3p=1/11.25=4/45 (3+5)/15p=4/45 p = 6 Time taken by Ajay alone to finish the work = 5p = 30 days Hence, Quantity I β€ Quantity II
P and Q can complete a piece of work individually in 12 days and 20 days, respectively. They start working together, but after 6 days, Q leaves the work...
Ratio of the work done by P, Q and R in one day is 5:3:7 respectively. They all together can complete the work in 35 days. Q and R worked on it for 20 d...
Shivam invested 25000 at 12% p.a. simple interest for βxβ months. If at the end of βxβ months, he received a total amount of Rs.30000. What is t...
'B' is 37.5% more productive than 'A'. Together, they can finish a task in 40 days. How many days would it take for 'A' alone to complete the entire task?
A and B together, B and C together and A and C together can complete a piece of work in 12 days, 11 days and 9 days respectively. Find the ratio ...
βAβ can do a piece of work in 8 days. βBβ can do 40% of the same work in 16 days. If they work together for the entire time and get paid Rs.1500...
βPβ alone can do 60% of a work in 18 days and βQβ alone can do 30% of the same work in 9 days. βPβ, βQβ and βRβ together can finish ...
A buffalo alone can plough field βAβ in 20 days. A Bull alone can plough the field βAβ in 32 days. Find the number of days taken by 2 bulls and ...
X men can complete the piece of work in 36 days and (X + 35) men can complete the same work in 14 days less than that of days taken by X men. Find the v...
A can finish a task by himself in 25 days, whereas B can finish the same task by himself in 10 days. A begins the task but stops after 5 days, at which ...