Question

"P" is able to finish a job in 20 days. "K" can complete the same job in 4 days less than "P." If they work together, how many days will it take for them to jointly complete 90% of the job?

A 5 days
B 8 days
C 12 days
D 18 days
Practice Next

Hey! Ask a query

🎓
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
  • 200 Questions with Detailed Solutions
  • Section-wise Coverage (GA, English, Quant & Reasoning)