Question
A can complete a work in 30 days, B in 24 days, and C in
20 days. A, B, and C work together for 5 days, after which B and C leave. How many more days will A take to complete the remaining work?Solution
Work done by A, B, and C together in 1 day = (1/30) + (1/24) + (1/20). LCM of 30, 24, and 20 is 120. Work done by A, B, and C in 1 day = (4 + 5 + 6)/120 = 15/120 = 1/8 of the total work. In 5 days, they complete 5/8 of the work. Remaining work = 1 − 5/8 = 3/8. A's rate of work = 1/30. Time taken by A to complete the remaining 3/8 of the work = (3/8) × 30 = 11.25 days. Ans. a
In 2016, which Indian Financial System method was introduced by RBI?
The currency of Switzerland is
Which ministry launched the Humsafar Policy to facilitate better services on National Highways?
Match the following Days with their respective days

Match List-I with List-II and choose the correct answer from the codes below:
To be granted Maharatna status, a company's average annual turnover over the last 3 years must exceed ________.
Of which of the following who was the first ever industrialist to get the Bharat Ratna?
In which year “Global gender gap index” was published for the first time?
When was the term "Uttarakhand" used for the first time in Uttar Pradesh administrative records?
Which of the following teams won the ICC Women's T20 World Cup 2020?