Question
A and B can complete a work in 12 days and 15 days
respectively. If they work together for 4 days and then B leaves, in how many days can A complete the remaining work?Solution
ATQ, A's daily work = 1/12 B's daily work = 1/15 A and B together do 1/12 + 1/15 = 3/20 of the work in one day. In 4 days, they complete 4 ร (3/20) = 3/5 of the work. Remaining work = [1 - (3/5)] = 2/5 A will complete the remaining work in (2/5) / (1/12) = 24/5 = 4.8 days.
Electrical fuse is used to interrupt excess of _________.
Which of the following statements best describes the relationship between static friction and the normal force?
Which Nobel Gas is also known as โStranger Gasโ?
The S.I. unit of the electric flux is
What type of image is always formed by a convex mirror?
The motion of a freely falling body is an example of ______________ accelerated motion.
Which of the following Instrument is used to measure humidity?
The Atom Bomb dropped in Nagasaki is an uncontrolled nuclear fission made up of:
The instrument which uses sound waves to measure the depth of oceans is โ
Mercalli scale is the instrument used for measuring the intensity of ___________.