      Question

      After working for 8 days, Rakhi finds that only 10

      percent of the work is completed. She employs Poonam who is 20 percent more efficient than Rakhi. How many more days will they together take to complete the remaining work?Β 
      A 360/7 days Correct Answer Incorrect Answer
      B 360/11 days Correct Answer Incorrect Answer
      C 340/11 days Correct Answer Incorrect Answer
      D 340/7 days Correct Answer Incorrect Answer

      Solution

      The correct answer is B