    Question

    A alone can complete a work in 18 days and B alone in 14

    days. Starting with A, they work on alternate days. The total work will be completed in:
    A 13(7/9) days Correct Answer Incorrect Answer
    B 15(7/9) days Correct Answer Incorrect Answer
    C 16(7/9) days Correct Answer Incorrect Answer
    D 14(7/9) days Correct Answer Incorrect Answer

    Solution

    The correct answer is B