Question
A alone can complete a work in 18 days and B alone in 14 days. Starting with A, they work on alternate days. The total work will be completed in:
More Previous year papers Questions
- The difference between the external and internal curved surface areas of a 7 cm long cylindrical metallic pipe is 110 cm². If the pipe is made of 302.5 cm³...
- The angle of elevation of a ladder leaning against a wall is 45 and the foot of the ladder is 10 m away from the wall. The length of the ladder
- Choose the most appropriate answer The value of (256)0.16 × (16)0.18
- The mode and the mean of grouped data are 27.5 and 28.5 respectively. Find the median, correct to two places of decimal, using empirical relation.
- In the given figure, Ð DBC = 65°, Ð BAC = 35° and AB = BC, then the measure of Ð ECD is equal to:
- Naman sells an item at ₹ x, after giving two successive discounts each of 10% on its marked price. If he does not give any discount on the marked price, he...
- The chemical name of the Vitamin B6 is
- The number of marbles in three bags is in the ratio of 2 : 3 : 4. If 12 marbles are added to each bag, then the ratio changed to 8 : 11 : 14. The total num...
- A cylindrical tank, 14 m in radius, contains water up to the depth of 7 m. What is the total area of the wetted surface? (Use π = 22/7)
- From a sample of 250 data scientists, determine the ratio of those proficient in Python to those proficient in R
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)