      Question

      A alone can complete a work in 18 days and B alone in 14

      days. Starting with A, they work on alternate days. The total work will be completed in:
      A 13(7/9) days Correct Answer Incorrect Answer
      B 15(7/9) days Correct Answer Incorrect Answer
      C 16(7/9) days Correct Answer Incorrect Answer
      D 14(7/9) days Correct Answer Incorrect Answer

      Solution

      The correct answer is B